Our energysaving bottom plate is nearly ready!
The fundaments with earth ankers are already placed, hereon there is mounted Styrodur (XPS) at the moment.
IMG_3114.jpg
Our energysaving bottom plate is nearly ready!
The fundaments with earth ankers are already placed, hereon there is mounted Styrodur (XPS) at the moment.
IMG_3114.jpg
Our bottom-plate is finally done!
After the floor heating and the reinforcement was completed, the time has come to pour the concrete bottom plate.
In total 30 trucks loaded with 700 tons of concrete were necessary.
20140817_152055.jpg
IMG_3124.jpg
20140820_110205.jpg
20140820_110003.jpg
On GHL construction site happens a lot.
Yesterday they begin to build up the steel scaffolding.
Bau.jpg
IMG_3303.jpg
IMG_3322.jpg
IMG_3331.jpg
Going up fast!
When do you expect to move in?